| 1936: |
|
April 25 Organizational Meeting Directors elected were H. O. Melby, R. M. Grimsrud of Westby, Melvin E. Olson, C. V. Gorman, Otto G. Henry and Nick Dorschied of Viroqua, Ray Clark of Cashton, A. J. Ristow of Genoa and J. M. Hora of Hillsboro. |
| 1937: |
|
June Office space rented in Westby-Coon Valley Bank Building
(NW corner of Main St. & State St. ) After first loan application approval by REA construction of lines was begun.
July 6 N. F. Leifer hired as Project Superintendent and Manager. |
| 1938: |
|
January 21 Martin Schye, H. R. Vergeroot and Trygve Ostrem farms are the first to be connected to newly built energized power lines southwest of Westby. |
| 1938: |
|
First Home Economist in Wisconsin working for cooperative hired. |
| 1946: |
|
Farm Wiring Advisor hired. |
| 1947: |
|
Two-way base to truck radio communication started. |
| 1957: |
|
December 7 New Westby Headquarters building dedicated. |
| 1961: |
|
N.F. Leifer and his wife, President H.O. Melby and Treasurer E.T. Smith killed
in traffic accident enroute home from the NRECA Annual Meeting in Dallas, TX. |
| 1961: |
|
Earl Jaeger hired as Manager. |
| 1966: |
|
Garage/Warehouse building built for Hillsboro Service Area on the intersection of Hwy 82 & 33. |
| 1969: |
|
First primary high voltage lines placed underground. |
| 1970: |
|
May Readstown Public Electric Utility purchased. |
| 1987: |
|
July 1 Merle Holden hired as Manager. |
| 1993: |
|
Major flooding of the Mississippi puts many meters under water. |
| 1998: |
|
July 27 Worst windstorm in VEC history knocks power out from
Stoddard to Cashton. Linemen work for 4 ½ days to restore everyones power. |
| 2001: |
|
Mike McMahon hired as Manager to replace the retiring
Merle Holden.
The Mississippi River reaches 16.41 feet at La Crosse causing damage
and outages along the river. |
| 2003: |
|
Installation of automated meter reading (AMR) begins and was completed in 2005. |
| 2007: |
|
August 18-19 & 21-24. Some of the worst flooding ever seen in service area.
New record for August rainfall. Widespread outages, some lasting up to 3 ½ days due to
wind, flooding, lightning, down trees, washed out underground lines. Restoration efforts hampered
by washed out roads, down trees & flooding. Crews from Riverland Energy, Adams-Columbia, Oakdale,
Scenic Rivers and Richland Electric Cooperatives aided in the recovery. |
| 2009: |
|
June 26th Vernon Electric Closes the doors at their Main St. office and out-buildings in Westby
and moves to its new headquarters at the intersection of Hwy. 27 and Saugstad Rd. |
| 2010: |
|
Mike McMahon retires as General Manager on May 17th and is replaced by Joe McDonald on June 1st. |
Stats in ten-year increments
| Year |
Miles of Lines |
# of Members |
kWh Used/ Member/Mo. |
kWh Sold |
Total Assets |
| 1938 |
423 |
903 |
33 |
360,283 |
$532,696 |
| 1948 |
1160 |
3760 |
192 |
8,657,965 |
$1,461,925 |
| 1958 |
1455 |
4689 |
593 |
33,418,107 |
$2,834,201 |
| 1968 |
1597 |
5352 |
917 |
58,595,407 |
$8,503,877 |
| 1978 |
1809 |
7128 |
1377 |
116,200,240 |
$10,440,648 |
| 1988 |
1890 |
7847 |
1277 |
119,455,390 |
$17,531,493 |
| 1998 |
1943 |
8931 |
1157 |
122,611,558 |
$26,805,415 |
| 2008 |
2095 |
10,828 |
1127 |
146,168,395 |
$43,596,804 |
|